What is the proper order of the electrical inspection according to the Florida Building Code?

  1. Underground inspection, rough-in inspection, final inspection

  2. Rough-in inspection, underground inspection, final inspection

  3. Underground inspection, final inspection, rough-in inspection

  4. Rough-in inspection, final inspection, underground inspection

The correct answer is: Underground inspection, rough-in inspection, final inspection

The proper order of the electrical inspection according to the Florida Building Code begins with the underground inspection, followed by the rough-in inspection, and concludes with the final inspection. The underground inspection is conducted first to ensure that all underground electrical conduits, cables, and grounding systems are properly installed and compliant before they are covered. This step is crucial to prevent any future issues that could arise from improper installation that would be inaccessible once the ground is filled in. Next in the sequence is the rough-in inspection, which occurs when the electrical wiring, boxes, and devices are installed but prior to covering them with walls or ceilings. This inspection verifies that the installation meets code requirements and safety standards, focusing on the integrity of the electrical system during the initial construction phase. Finally, the final inspection takes place once all the electrical work is completed and the building is near occupancy. This inspection ensures that the entire electrical system is functional, safe, and meets the necessary codes before the building is occupied. This sequential approach is essential for maintaining safety, compliance, and ensuring that all electrical installations are thoroughly checked at various stages to prevent issues later in the construction process.