Study for the Florida Building Code Exam with multiple choice questions and detailed explanations. Get fully prepared with our comprehensive practice exam to enhance your knowledge.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


When must a permit application be submitted after emergency repairs are performed?

  1. 5 days from completion

  2. The next working day

  3. 5 days from commencement

  4. 7 days from commencement

The correct answer is: The next working day

The correct answer indicates that a permit application must be submitted the next working day after emergency repairs are performed. This requirement is designed to ensure that all emergency repairs are documented promptly for regulatory compliance and safety inspections. It highlights the urgency of formalizing repairs that need immediate attention and prevents prolonged situations where unpermitted work could lead to safety hazards or code violations. Timely submission helps maintaining the integrity of building standards and allows for city or county officials to assess the work done to ensure compliance with the Florida Building Code. Other options referencing submission after several days do not align with the immediate nature of emergency responses required in such scenarios.